nerdexam
PRINCE2

PRINCE2-AGILE-FOUNDATION · Question #47

Which statement about the 'embrace change' target is CORRECT?

The correct answer is D. It encourages the customer to raise new ideas. You've hit your limit · resets 5am (America/New_York)

PRINCE2 Agile Behaviors and Concepts

Question

Which statement about the ’embrace change' target is CORRECT?

Options

  • AIt minimizes the time needed to train a new team member
  • BIt reduces the planning of dependencies between projects
  • CIt reduces testing in order to meet deadlines
  • DIt encourages the customer to raise new ideas

How the community answered

(36 responses)
  • A
    3% (1)
  • B
    6% (2)
  • C
    14% (5)
  • D
    78% (28)

Explanation

You've hit your limit · resets 5am (America/New_York)

Topics

#embrace change#agile targets#customer collaboration#PRINCE2 Agile behaviors

Community Discussion

No community discussion yet for this question.

Full PRINCE2-AGILE-FOUNDATION Practice