PRINCE2-AGILE-FOUNDATION · Question #19
What is the purpose of the 'progress' practice?
The correct answer is A. To provide a forecast for the project's viability. The Progress practice in PRINCE2 Agile is focused on providing a forecast of the project's viability by monitoring actual progress against plans and predicting future performance. It ensures that decisions can be made based on current status and trends, enabling timely…
Question
What is the purpose of the 'progress' practice?
Options
- ATo provide a forecast for the project's viability
- BTo identify and assess opportunities and threats
- CTo identify the user needs and requirements
- DTo establish accountability for the project
How the community answered
(24 responses)- A71% (17)
- B17% (4)
- C8% (2)
- D4% (1)
Explanation
The Progress practice in PRINCE2 Agile is focused on providing a forecast of the project's viability by monitoring actual progress against plans and predicting future performance. It ensures that decisions can be made based on current status and trends, enabling timely interventions if This practice involves collecting progress data, reviewing milestones, updating forecasts, and communicating status to stakeholders. Forecasting viability includes assessing whether the project remains aligned with business justification and expected benefits.