PRINCE2-AGILE-FOUNDATION · Question #117
Which statement about the 'protect the level of quality' target is CORRECT?
The correct answer is D. It delivers the early realization of benefits. You've hit your limit · resets 5am (America/New_York)
Flexible Delivery Targets
Question
Which statement about the ’protect the level of quality' target is CORRECT?
Options
- AIt is achieved by allowing enough time for testing
- BIt is achieved by using the same team members
- CIt gives confidence on the progress of the project
- DIt delivers the early realization of benefits
How the community answered
(39 responses)- B3% (1)
- C3% (1)
- D95% (37)
Explanation
You've hit your limit · resets 5am (America/New_York)
Topics
#quality protection#flexible delivery#benefits realization#agile targets