PRINCE2-AGILE-FOUNDATION · Question #116

Which statement explains the target 'be on time and hit deadlines' for flexible delivery?

The correct answer is A. It reduces testing in order to meet deadlines. You've hit your limit · resets 5am (America/New_York)

Flexible Delivery Targets

Question

Which statement explains the target ‘be on time and hit deadlines' for flexible delivery?

Options

  • AIt reduces testing in order to meet deadlines
  • BIt sets the project baseline at the correct level
  • CIt enables team dynamics to remain the same
  • DIt improves the supplier's reputation with the customer

How the community answered

(36 responses)
  • A
    92% (33)
  • B
    3% (1)
  • C
    6% (2)

Explanation

You've hit your limit · resets 5am (America/New_York)

Topics

#flexible delivery#deadlines#testing trade-offs#time management