nerdexam
PMIPMI

PMP · Question #965

PMP Question #965: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #965. The question stem and answer options stay visible for context.

Submitted by yousef_jo· Apr 18, 2026People

Question

During user acceptance testing, a project sponsor asks the project manager to add a couple of features. To meet the firm go-live date, the project team will need to work overtime. What should the project manager do?

Options

  • ASubmit an emergency change request and assign tasks to the team.
  • BRequest approval for overtime and a bonus to deliver on time.
  • CInform the sponsor that the project team cannot commit to more work.
  • DConsult with the project team and provide options to the sponsor.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Change Management#Stakeholder Management#Resource Management#Team Collaboration
Full PMP PracticeBrowse All PMP Questions