nerdexam
PMI

PMP · Question #954

After releasing the first deliverable of the project, one of the impacted departments refused to use the system because they believe that it adds more work. What could the project manager have done to

Sign in or unlock PMP to reveal the answer and full explanation for question #954. The question stem and answer options stay visible for context.

Submitted by the_admin· Apr 18, 2026People

Question

After releasing the first deliverable of the project, one of the impacted departments refused to use the system because they believe that it adds more work. What could the project manager have done to prevent this?

Options

  • ADeployed a user survey
  • BReviewed organizational standard policies
  • CCreated an escalation plan
  • DConducted a stakeholder analysis

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Stakeholder Analysis#Stakeholder Engagement#Preventive Action#User Adoption
Full PMP Practice