PMI
PMP · Question #954
After releasing the first deliverable of the project, one of the impacted departments refused to use the system because they believe that it adds more work. What could the project manager have done to
Sign in or unlock PMP to reveal the answer and full explanation for question #954. The question stem and answer options stay visible for context.
Submitted by the_admin· Apr 18, 2026People
Question
After releasing the first deliverable of the project, one of the impacted departments refused to use the system because they believe that it adds more work. What could the project manager have done to prevent this?
Options
- ADeployed a user survey
- BReviewed organizational standard policies
- CCreated an escalation plan
- DConducted a stakeholder analysis
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Stakeholder Analysis#Stakeholder Engagement#Preventive Action#User Adoption