nerdexam
PMIPMI

PMP · Question #896

PMP Question #896: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #896. The question stem and answer options stay visible for context.

Submitted by kevin_r· Apr 18, 2026People

Question

All activities for Project A are ahead of schedule, except for one activity that is on the critical path. The resource manager is requesting that the team members join Project B, which is an important project in the organization that is behind schedule. What should the project manager do?

Options

  • AAsk the stakeholders to pause Project A because Project B is more important.
  • BRelease the team members from Project A who are not working on a critical path activity,
  • CAgree to reassign all team members to Project B due to its importance.
  • DRetain the team members on Project A and complete the planned activities as committed.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Resource Management#Project Commitments#Critical Path#Stakeholder Management
Full PMP PracticeBrowse All PMP Questions