All activities for Project A are ahead of schedule, except for one activity that is on the critical path. The resource manager is requesting that the team members join Project B, which is an important

The correct answer is D. Retain the team members on Project A and complete the planned activities as committed.. Despite requests to reassign resources to another important project, the project manager should retain team members on their project to complete committed activities, especially when it's largely ahead of schedule with one critical path item remaining.

Submitted by kevin_r· Apr 18, 2026People

Question

All activities for Project A are ahead of schedule, except for one activity that is on the critical path. The resource manager is requesting that the team members join Project B, which is an important project in the organization that is behind schedule. What should the project manager do?

Options

  • AAsk the stakeholders to pause Project A because Project B is more important.
  • BRelease the team members from Project A who are not working on a critical path activity,
  • CAgree to reassign all team members to Project B due to its importance.
  • DRetain the team members on Project A and complete the planned activities as committed.

How the community answered

(48 responses)
  • A
    2% (1)
  • B
    10% (5)
  • C
    6% (3)
  • D
    81% (39)

Why each option

Despite requests to reassign resources to another important project, the project manager should retain team members on their project to complete committed activities, especially when it's largely ahead of schedule with one critical path item remaining.

AAsk the stakeholders to pause Project A because Project B is more important.

Asking stakeholders to pause Project A when it is largely on track and has existing commitments would be a drastic measure, going against the project manager's responsibility to deliver their project as planned, without a clear, higher organizational mandate.

BRelease the team members from Project A who are not working on a critical path activity,

While seemingly a compromise, releasing team members from Project A, even those not directly on the critical path, could still reduce the project's overall capacity and its ability to maintain its 'ahead of schedule' status or efficiently manage the single critical path activity, thereby putting commitments at risk.

CAgree to reassign all team members to Project B due to its importance.

Agreeing to reassign all team members would completely derail Project A and its commitments, which is contrary to the project manager's core responsibility, especially when Project A is performing well and has its own critical activities.

DRetain the team members on Project A and complete the planned activities as committed.Correct

The project manager's primary responsibility is to deliver Project A as committed, especially since it is largely ahead of schedule, despite one critical path activity that still requires focused attention. Removing team members to support another project (B), even if B is important and behind, risks jeopardizing Project A's successful completion and established commitments. Unless there is a formal organizational directive to reprioritize, the PM should protect the resources allocated to their project to ensure its planned delivery.

Concept tested: Project resource allocation, commitment protection, critical path management

Source: https://www.pmi.org/pmbok-guide-standards/resource-management

Topics

#Resource Management#Project Commitments#Critical Path#Stakeholder Management