PMP · Question #801
A company has rolled out the latest retail management system, and the project has been handed over to operations. The operations team finds that many of the day-to-day requirements are not covered in
The correct answer is A. Involved operations stakeholders during planning. To prevent operational issues after project handover, the project lead should have engaged operations stakeholders early in the planning phase to ensure their day-to-day requirements were integrated into the system design. This proactive involvement helps align the system with ac
Question
Options
- AInvolved operations stakeholders during planning
- BReviewed the project management plan
- CIncreased support hours for the hours of operation
- DCreated a detailed operations manual
How the community answered
(25 responses)- A76% (19)
- B4% (1)
- C8% (2)
- D12% (3)
Why each option
To prevent operational issues after project handover, the project lead should have engaged operations stakeholders early in the planning phase to ensure their day-to-day requirements were integrated into the system design. This proactive involvement helps align the system with actual operational needs, preventing disconnects and issues post-deployment.
Involving operations stakeholders during the planning phase ensures that their functional requirements, daily processes, and support needs are captured and incorporated into the project scope and design. This prevents the development of a system that is technically sound but operationally deficient, leading to a smoother transition and fewer post-implementation issues.
Reviewing the project management plan after the fact would not address the root cause of the initial failure to include operational requirements during planning.
Increasing support hours is a reactive measure to an existing problem, not a proactive action to avoid the problem during the initial planning phase.
While an operations manual is helpful, it describes how to use an existing system; it does not ensure that the system itself meets operational requirements if those requirements were never properly captured.
Concept tested: Stakeholder engagement and requirements gathering
Source: https://www.pmi.org/learning/library/stakeholder-engagement-project-management-10029
Topics
Community Discussion
3Confirmed A on my exam last month. If you do not bring operations stakeholders into planning, you will never capture what the day-to-day users actually need, and the handover falls apart.
Confirmed A on my exam last month. The clue for me was the day-to-day requirements being missed, which screams the people actually using the system were never in the room during planning.
A is the fix. But does PMP treat ops handoff as stakeholder engagement or requirements gathering?