nerdexam
PMIPMI

PMP · Question #796

PMP Question #796: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #796. The question stem and answer options stay visible for context.

Submitted by anjalisingh· Apr 18, 2026People

Question

A project manager is using a hybrid approach to comply with a regulatory requirement. The planning and closing phases will use a predictive approach, and the execution phase will use an iterative approach. During the second sprint review, the project sponsor requested a change in priority tor some of the product backlog items. What should the project manager do as a servant leader?

Options

  • AAsk the sponsor to submit a change request to the change control board (CCB)
  • BSupport the product owners decision to change the priority of the product backlog items
  • CAccept the request and include the product backlog items in the next sprint
  • DReview the impact of the change on the schedule management plan baseline

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Servant Leadership#Agile Roles#Product Backlog Management#Stakeholder Engagement
Full PMP PracticeBrowse All PMP Questions