PMP Question #722: Real Exam Question with Answer & Explanation

The correct answer is A. Agree with the project team on a suitable collaboration and make sure information is shared at all. To avoid future communication delays, the project manager should collaborate with the project team to agree on suitable communication channels, ensuring information is shared effectively among all members.

Submitted by luis.pe· Apr 18, 2026People

Question

A project manager is working with the team to deliver a project in a company that uses different delivery methods. The project manager is concerned about the communication channels currently suggested by the project management office (PMO) because some information is taking too much time to reach the team members, causing negative consequences for delivery. How should the project manager avoid this situation in the future?

Options

  • AAgree with the project team on a suitable collaboration and make sure information is shared at all
  • BUse the same methods until the end of the current delivery and suggest new ones during the
  • CRefer to the policies and frameworks used at the company enterprise level and inform the project
  • DTell the sponsor that the project manager will use their own communication model to ensure on-

Explanation

To avoid future communication delays, the project manager should collaborate with the project team to agree on suitable communication channels, ensuring information is shared effectively among all members.

Common mistakes.

  • B. Continuing with ineffective communication methods for the remainder of the delivery will perpetuate the negative consequences, directly contradicting the goal of preventing such issues in the future.
  • C. Simply referring to enterprise-level policies without adapting or changing the methods for the specific project will not solve the problem if those policies are the source of the communication inefficiency.
  • D. unilaterally declaring a personal communication model to the sponsor, without team agreement or consideration of organizational standards, is an autocratic approach that could lead to disengagement and lack of support from both the team and the PMO.

Concept tested. Communication Management, Team Collaboration

Reference. https://www.pmi.org/learning/library/project-communications-management-8677