PMP · Question #669
PMP Question #669: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #669. The question stem and answer options stay visible for context.
Question
A key project team member is out on sick leave in the middle of a critical project iteration. The project sponsor learns that any delay with the end-of-iteration release will displease the business stakeholders. Although all team members are cross-functional, they are also working close to full capacity. What should the project manager do to address this situation?
Options
- ADiscuss this with the team so they can complete the work of the unavailable team member and
- BDiscuss this with the team so they are able to reprioritize critical tasks and aim for the release
- CDiscuss this with the sponsor and hold a meeting with the stakeholders so all of the team
- DDiscuss the issues with the sponsor to fully convey the problem of the unavailable resource and
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.