nerdexam
PMIPMI

PMP · Question #62

PMP Question #62: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #62. The question stem and answer options stay visible for context.

Submitted by kev92· Apr 18, 2026People

Question

A third-party supplier demands payment for the services provided for a project. The agreement was that payment would be made after the organization receives payment from the client. The third-party supplier lacks the capital to meet their payroll and has informed the project manager that if they do not receive payment quickly, they will withdraw team members from the project. What should the project manager do?

Options

  • AExplain the third-party supplier situation to the client and request payment.
  • BInform the client that the project must be delayed until payment is received.
  • CReassign resources from other projects to pay the third-party supplier.
  • DProcess a bank loan to pay the payroll of the third-party supplier.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Stakeholder Communication#Risk Mitigation#Vendor Management#Contract Management
Full PMP PracticeBrowse All PMP Questions