PMP · Question #601
PMP Question #601: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #601. The question stem and answer options stay visible for context.
Question
A project manager is leading a hybrid project and is collaborating with the client to develop the project contract. Some delays have been experienced due to unforeseen technical difficulties and new dependencies. However, the project manager is optimistic about recovering the delays in the upcoming sprints. A key stakeholder asked the project manager if the contract deadlines can be met. What should the project manager do first?
Options
- AClarify the current work progress, causes for delays, existing risks, and planned corrective
- BAsk the stakeholder to remain calm and confirm that they are participating in all team meetings.
- CStudy the contract terms and deadlines to ensure they are not under risk and confirm them with
- DSubmit a request for extra time and budget related to the dependencies and technical difficulties.