PMIPMI
PMP · Question #6
PMP Question #6: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #6. The question stem and answer options stay visible for context.
Submitted by layla.eg· Apr 18, 2026People
Question
A project team is implementing a hosted system for a third party. Just before going live, the customer asks the project team to include additional functionality. The project team identified risks to the delivery date and informed the project manager that some of the requested functions are in conflict with the agreed scope. What should the project manager do?
Options
- ADiscuss with the customer the risks identified and team's concerns
- BDiscuss with the team, estimate the effort, and raise a change request
- CAsk the customer to go live and add the new functionality in the backlog
- DAsk the team to deliver the functionality on the agreed go-live date
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Stakeholder Communication#Change Management#Scope Management#Risk Management