All project team members refer to the project manager for various decisions. This causes delays for some tasks. as the project manager is usually preoccupied in meetings throughout the day. What should the project manager do to prevent these delays?
Options
- AMeet with the team in 2 weeks to respond to all of the open tasks.
- BReview the Pareto diagram to identify the source of delays.
- CDelegate the decision-making authority of some tasks to the team.
- DConsolidate the decision-making authority to remain with the project manager.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Delegation#Decision-making#Team empowerment#Bottleneck management