nerdexam
PMIPMI

PMP · Question #58

PMP Question #58: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #58. The question stem and answer options stay visible for context.

Submitted by kevin_r· Apr 18, 2026People

Question

Halfway through a project, the project sponsor is replaced by another peer who was not previously engaged in the project. The new project sponsor has rejected most of the project artifacts, and the team did not get the latest increment approved on the current iteration. Stakeholders are not feeling confident about the project outcome. What should the project manager have done to prevent this situation?

Options

  • APerformed a stakeholder analysis when the sponsor joined the project
  • BHeld a governance meeting to review the project increment
  • CEscalated the issue to ensure the increment would be approved
  • DConducted a product iteration review with the new project sponsor

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Stakeholder Analysis#Stakeholder Engagement#Preventive Actions#Project Sponsor Management
Full PMP PracticeBrowse All PMP Questions