nerdexam
PMIPMI

PMP · Question #565

PMP Question #565: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #565. The question stem and answer options stay visible for context.

Submitted by deeparc· Apr 18, 2026People

Question

A team is preparing the closing phase and building a plan for the next phase. One of the project sponsors is complaining that the last phase had some quality deliverable issues. However, the quality acceptance document was signed. What should the project manager do?

Options

  • APostpone the next project phase until the impact of the quality issues is assessed.
  • BReopen the quality acceptance documentation to add the sponsor's complaints.
  • CSchedule a quality review meeting and include the sponsor's complaints.
  • DReview best practices and lessons learned and apply them to the project plan.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Stakeholder Engagement#Quality Management#Issue Resolution#Lessons Learned
Full PMP PracticeBrowse All PMP Questions