PMIPMI
PMP · Question #565
PMP Question #565: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #565. The question stem and answer options stay visible for context.
Submitted by deeparc· Apr 18, 2026People
Question
A team is preparing the closing phase and building a plan for the next phase. One of the project sponsors is complaining that the last phase had some quality deliverable issues. However, the quality acceptance document was signed. What should the project manager do?
Options
- APostpone the next project phase until the impact of the quality issues is assessed.
- BReopen the quality acceptance documentation to add the sponsor's complaints.
- CSchedule a quality review meeting and include the sponsor's complaints.
- DReview best practices and lessons learned and apply them to the project plan.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Stakeholder Engagement#Quality Management#Issue Resolution#Lessons Learned