Question
A project is on its second iteration out of six. The team realizes that a key deliverable will depend on the acquisition of a new device. What should the project manager do?
Options
- AInvite the stakeholders to discuss prioritization of a new deliverable.
- BDetail the reason for the deliverable delay in the status report.
- CRegister a risk and escalate it to the project sponsor.
- DInclude the responsibility for acquisition with the core team.