PMP · Question #494
PMP Question #494: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #494. The question stem and answer options stay visible for context.
Submitted by fernanda_arg· Apr 18, 2026People
Question
The client will not agree to closure, claiming that the project team has not performed the code inspections mandated in the development contract. The project team has performed the code inspections, however the records are not complete. What should the project manager do?
Options
- ASeek expert legal advice on the interpretation of the clauses in the contract
- BHold a meeting with the project team project sponsor and the client to agree to the further work
- CClose the project and hand over the deliverables to the client
- DHold a lessons learned workshop with the project team and project sponsor to avoid contractual
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Stakeholder Management#Conflict Resolution#Project Closure#Communication Management