An organization is introducing agile to its projects. During an informal discussion the project manager learned that team members who are currently working on different teams are discussing how they w

The correct answer is D. The project manager should indicate that the team members have already been assigned to a. In an organization transitioning to Agile, team members are expressing a desire to form new teams. The project manager should acknowledge their existing assignments while considering their input for future team formation.

Submitted by weili_xi· Apr 18, 2026People

Question

An organization is introducing agile to its projects. During an informal discussion the project manager learned that team members who are currently working on different teams are discussing how they would like to be together on the same team. What should the project manager do?

Options

  • AThe project manager should not allow resources to choose teams because the project manager
  • BThe project manager should not allow resources to choose on which team they would like to work
  • CThe project manager should allow the resources to periodically choose on which team they would
  • DThe project manager should indicate that the team members have already been assigned to a

How the community answered

(40 responses)
  • A
    3% (1)
  • B
    8% (3)
  • C
    15% (6)
  • D
    75% (30)

Why each option

In an organization transitioning to Agile, team members are expressing a desire to form new teams. The project manager should acknowledge their existing assignments while considering their input for future team formation.

AThe project manager should not allow resources to choose teams because the project manager

This statement is an overgeneralization; self-organizing teams are encouraged in agile, and some input in team formation can be beneficial.

BThe project manager should not allow resources to choose on which team they would like to work

This statement is an overgeneralization; while complete freedom of choice might not always be feasible, some input or consideration of preferences can improve team morale and performance.

CThe project manager should allow the resources to periodically choose on which team they would

Periodically allowing resources to choose teams might lead to instability and disruption, especially in the initial stages of agile adoption, when consistency is often needed.

DThe project manager should indicate that the team members have already been assigned to aCorrect

While self-organizing teams are a core agile principle, this applies to how teams manage their work, not necessarily initial team formation when a project or organization is just starting or transitioning. If team members have already been officially assigned to specific teams, the project manager needs to acknowledge and uphold those current assignments, while potentially considering preferences for future team compositions.

Concept tested: Agile team formation and self-organization

Source: https://agilemanifesto.org/principles.html

Topics

#Agile Team Formation#Team Assignment#Project Manager Communication#Self-Organizing Teams