nerdexam
PMIPMI

PMP · Question #446

PMP Question #446: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #446. The question stem and answer options stay visible for context.

Submitted by akirajp· Apr 18, 2026People

Question

A project manager has been appointed to a multimillion-dollar project. The project is considered to be high risk since no similar projects have been undertaken before and there is no historical data. Some external stakeholders are reluctant to provide support. What approach should the project manager take?

Options

  • AExamine the plans, processes, policies, and knowledge that are specific to the organization
  • BEstablish dialogue with stakeholders on the project constraints, assumptions, and critical inputs
  • CConvince senior management to close the project since the project lacks sponsorship and is
  • DHost a project team meeting, then update the risk register and the project management plan

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Stakeholder Engagement#Risk Management#Communication Planning#Expectation Management
Full PMP PracticeBrowse All PMP Questions