A project manager has been appointed to a multimillion-dollar project. The project is considered to be high risk since no similar projects have been undertaken before and there is no historical data. Some external stakeholders are reluctant to provide support. What approach should the project manager take?
Options
- AExamine the plans, processes, policies, and knowledge that are specific to the organization
- BEstablish dialogue with stakeholders on the project constraints, assumptions, and critical inputs
- CConvince senior management to close the project since the project lacks sponsorship and is
- DHost a project team meeting, then update the risk register and the project management plan
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Stakeholder Engagement#Risk Management#Communication Planning#Expectation Management