nerdexam
PMIPMI

PMP · Question #434

PMP Question #434: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #434. The question stem and answer options stay visible for context.

Submitted by satoshi_tk· Apr 18, 2026People

Question

A technical manager newly appointed by the client, visits the project site to verify the project deliverables. The technical manager feels that the project manager has not been providing enough information. What should the project manager do first to resolve this situation?

Options

  • AUpdate the issue log and escalate to the project sponsor
  • BIdentify the lack of information as a risk and update the risk register
  • CSchedule more frequent meetings with the technical manager
  • DReview and update the stakeholder engagement plan

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Stakeholder Management#Communication Management#Stakeholder Engagement Plan#Issue Resolution
Full PMP PracticeBrowse All PMP Questions