During the retrospective ceremony, the agile team is talking about the product owner's expectations not being met. What should the project manager have done at the beginning of the project?

The correct answer is D. Communicated project vision and sprint goals clearly to the team. To ensure product owner expectations are met, the project manager (or Scrum Master) should have clearly communicated the project vision and sprint goals to the team from the outset.

Submitted by anna_se· Apr 18, 2026People

Question

During the retrospective ceremony, the agile team is talking about the product owner's expectations not being met. What should the project manager have done at the beginning of the project?

Options

  • ADefined the expected agile team contribution in the creation of the backlog
  • BAssessed the capabilities of the agile team and planned for the required training
  • CDefined the team ground rules and shared project vision
  • DCommunicated project vision and sprint goals clearly to the team

How the community answered

(18 responses)
  • A
    6% (1)
  • B
    11% (2)
  • C
    6% (1)
  • D
    78% (14)

Why each option

To ensure product owner expectations are met, the project manager (or Scrum Master) should have clearly communicated the project vision and sprint goals to the team from the outset.

ADefined the expected agile team contribution in the creation of the backlog

Defining the team's contribution to backlog creation is important, but a lack of clarity here might lead to inefficient backlog management, not necessarily unmet Product Owner expectations regarding the *product itself*.

BAssessed the capabilities of the agile team and planned for the required training

Assessing team capabilities and planning training addresses performance issues or skill gaps, but it doesn't directly solve a misalignment with Product Owner expectations which stems from a lack of understanding of the product's objectives.

CDefined the team ground rules and shared project vision

Defining team ground rules fosters team cohesion and efficiency, but while important, it doesn't directly address the critical communication of what needs to be built to meet the Product Owner's strategic vision.

DCommunicated project vision and sprint goals clearly to the teamCorrect

Clear communication of the project vision and sprint goals is fundamental in agile, serving as the guiding north star for the team. This ensures the team understands what they are trying to achieve and why, enabling them to prioritize, make informed decisions, and align their work with the Product Owner's expectations and overall project objectives from the beginning.

Concept tested: Agile communication, project vision, sprint goals

Source: https://www.scrum.org/resources/scrum-guide