nerdexam
PMI

PMP · Question #390

The project manager is having difficulty obtaining approval of the project requirements because there is disagreement among the project stakeholders. This issue is putting the project schedule at…

The correct answer is C. Identify the source of the disagreement. When stakeholder disagreement risks the project schedule by delaying requirement approval, the project manager should first identify the root cause of the disagreement.

Submitted by jaden.t· Apr 18, 2026People

Question

The project manager is having difficulty obtaining approval of the project requirements because there is disagreement among the project stakeholders. This issue is putting the project schedule at risk. What should the project manager do first to facilitate the approval of project requirements'?

Options

  • AReview the project charter
  • BPerform a stakeholder analysis
  • CIdentify the source of the disagreement
  • DHold a team-building event

How the community answered

(43 responses)
  • A
    2% (1)
  • B
    9% (4)
  • C
    81% (35)
  • D
    7% (3)

Why each option

When stakeholder disagreement risks the project schedule by delaying requirement approval, the project manager should first identify the root cause of the disagreement.

AReview the project charter

Reviewing the project charter might provide high-level objectives but will not directly reveal the specific reasons for disagreement among stakeholders regarding detailed requirements.

BPerform a stakeholder analysis

While performing a stakeholder analysis is crucial for understanding stakeholders, it's typically done earlier in planning; at this stage, the problem is known disagreement, so the focus should be on why they disagree, which is part of conflict resolution rather than initial analysis.

CIdentify the source of the disagreementCorrect

To facilitate approval when there is disagreement among stakeholders, the project manager must first understand why they disagree. Identifying the source of the disagreement will provide the necessary insight to develop a targeted strategy to resolve the conflict and move towards requirement approval.

DHold a team-building event

A team-building event is a general approach to improve team cohesion and may not directly address specific technical or business disagreements related to project requirements.

Concept tested: Conflict resolution in project management

Source: https://www.pmi.org/learning/library/conflict-management-skills-project-managers-8580

Topics

#Stakeholder Management#Requirements Management#Conflict Resolution#Communication

Community Discussion

4
Carlos M.Carlos M.May 29, 2026

C is the right call here. You can't resolve a disagreement if you don't know what's driving it, so identifying the source of the conflict has to happen before anything else. A and B are reasonable steps in general but they're too indirect when the schedule is already at risk and you need to unblock approvals fast. D is a trap answer that sounds nice but team-building doesn't fix conflicting requirements.

24
Prof. SaraProf. SaraJun 5, 2026

C is correct because before you can resolve a disagreement you have to find the root cause, which aligns with the People domain focus on conflict resolution. Think of the mnemonic RAD: Root cause, Analyze stakeholders, then Decide on the approach. Quick question for the group: if the disagreement turns out to be a fundamental difference in business objectives rather than a simple misunderstanding, would that change your next step toward formal stakeholder analysis or would you go straight to the charter to validate the original scope?

4
Luis F.Luis F.Jun 7, 2026

Leaned toward B first but you have to find the root cause before analyzing.

0
Prof. SaraProf. SaraJun 8, 2026

Exactly right, root cause identification must come before analysis, and remember the mnemonic R-C-A (Root Cause Analysis) maps directly to Domain 4 troubleshooting objectives where identifying precedes resolving.

0
Full PMP Practice