Question
Two weeks after the approval of the project management plan for a global project, the project manager noticed that it was approved based on a different level of understanding by international stakeholders and is not what the project manager presented for approval. What should the project manager have done to prevent this from happening?
Options
- ASent the meeting minutes to the stakeholders after the kick-off meeting
- BReviewed all the approvals immediately after the kick-off meeting was over
- CRan separate kick-off meetings for each culture and time zone
- DValidated each stakeholder's understanding during the kick-off meeting
Unlock PMP to see the answer