PMP Question #365: Real Exam Question with Answer & Explanation

The correct answer is A: Keep the stakeholder informed and consult with them based on their needs. Keep the stakeholder informed and consult with them based on their needs is the best approach. This will ensure that the stakeholder is kept up to date on the project's progress and can provide input or guidance when necessary. It is important to consult with the stakeholder to u

Submitted by viktor_hu· Apr 18, 2026People

Question

A member of the board of directors is the sponsor of a project that is important to the organization. This stakeholder has many other priorities and is not currently engaged in the project activities. How should the stakeholder be engaged in the project?

Options

  • AKeep the stakeholder informed and consult with them based on their needs
  • BInvolve the stakeholder in governance and decision making
  • CConsult with the stakeholder and increase their level of interest
  • DThe stakeholder needs to be made aware of the project progress

Explanation

Keep the stakeholder informed and consult with them based on their needs is the best approach. This will ensure that the stakeholder is kept up to date on the project's progress and can provide input or guidance when necessary. It is important to consult with the stakeholder to understand their needs and priorities and to align the project with those as much as possible.

Topics

#Stakeholder Management#Sponsor Management#Engagement Strategies#Communication Management