Question

A project manager is leading an in-house company project in its very early stages. This current project is similar to another project that ended a year ago. What should the project manager do to analyze the involved stakeholders?

Options

  • ALower the priority of stakeholder engagement as the stakeholders already have knowledge of this
  • BUse lessons learned from the previous project as a guide for the current project's stakeholder
  • CRefer to the stakeholder register from the previous project as it was similar to the current project
  • DDocument in the risk register that the current project may have different stakeholders than the

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Stakeholder Management#Lessons Learned#Organizational Process Assets#Stakeholder Analysis
Full PMP PracticeBrowse All PMP Questions