PMP · Question #338
PMP Question #338: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #338. The question stem and answer options stay visible for context.
Question
A project manager meets with external stakeholders to explain the objectives and outline expectations for a new project. A key stakeholder appears to support the project, with the condition that other unrelated projects will receive financial support. Due to cultural sensitivities, the project manager is reluctant to be direct with the key stakeholder on this matter. The project cannot proceed without the support of this stakeholder. What should the project manager do?
Options
- AProceed with the project without allowing scope creep to occur
- BUse the contingency funds to provide support for the requested projects
- CCancel the project since the stakeholder's request is out of scope
- DInform the sponsor and document the request in the stakeholder engagement plan
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.