nerdexam
PMIPMI

PMP · Question #33

PMP Question #33: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #33. The question stem and answer options stay visible for context.

Submitted by satoshi_tk· Apr 18, 2026People

Question

A project manager has been assigned a low-priority project that includes new team members with no previous formal project experience. The project team has requested deadline extensions for the first development increment twice already. What should the project manager do to support the team?

Options

  • AProvide feedback to the team using project performance evaluations.
  • BInclude buffer time in the schedule to absorb future delays.
  • CEscalate the impact on the schedule to the project sponsor.
  • DCreate a change request to extend the project's duration and costs.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Team management#Performance feedback#Team development#Coaching
Full PMP PracticeBrowse All PMP Questions