PMI
PMP · Question #292
PMP Question #292: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #292. The question stem and answer options stay visible for context.
Submitted by fernanda_arg· Apr 18, 2026People
Question
From previous lessons learned working with a client, a project manager notes that the client's turn-around times on documents sent for approval were very slow and well outside of the agreed timelines. At the initial kick-off meeting with the same client, how should the project manager approach this issue for the new project?
Options
- AUpdate the project risk register with the potential for delays.
- BInform the client that extra resources will be added to give the client more time for reviews.
- CWork with the client on an acceptable amount of time for document approval.
- DInform the client of their responsibility in relation to document approval.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Lessons Learned#Stakeholder Engagement#Expectation Management#Communication Planning