nerdexam
PMI

PMP · Question #243

A project to build a new energy plant was just completed. However, a few days before operation of the plant, the local community protested and closed access to the plant. They argue that an important

The correct answer is A. Stakeholder engagement plan. Community protests citing lack of consultation and environmental impact immediately after project completion point directly to a failure in stakeholder engagement, requiring the project manager to verify the relevant plan.

Submitted by the_admin· Apr 18, 2026People

Question

A project to build a new energy plant was just completed. However, a few days before operation of the plant, the local community protested and closed access to the plant. They argue that an important natural reserve was impacted and prior consultation was not done by the project team. What should the project manager verify first?

Options

  • AStakeholder engagement plan
  • BCost-benefit analysis
  • CBusiness case
  • DRisk management plan

How the community answered

(33 responses)
  • A
    70% (23)
  • B
    3% (1)
  • C
    18% (6)
  • D
    9% (3)

Why each option

Community protests citing lack of consultation and environmental impact immediately after project completion point directly to a failure in stakeholder engagement, requiring the project manager to verify the relevant plan.

AStakeholder engagement planCorrect

The protest specifically mentions a lack of prior consultation and impact on a natural reserve, pointing directly to a failure in identifying, analyzing, and engaging with key stakeholders, particularly the local community and environmental groups. The Stakeholder Engagement Plan dictates how and when stakeholders should be involved, and verifying it will reveal if these groups were identified and if the planned engagement activities were executed effectively.

BCost-benefit analysis

Cost-benefit analysis is about financial viability, not stakeholder consultation or environmental impact.

CBusiness case

The business case justifies the project's existence but does not detail the execution of stakeholder engagement.

DRisk management plan

While lack of consultation is a risk, the immediate problem is a failure in engagement, and the Stakeholder Engagement Plan specifically addresses how to manage these relationships, making it the most relevant document to check first for this specific issue.

Concept tested: Stakeholder management and engagement

Topics

#Stakeholder Engagement#Community Relations#Issue Management

Community Discussion

3
Anjali D.Anjali D.Mar 11, 2026

A is correct. Our group universally agreed on this one because the community protest is a classic stakeholder engagement failure, so the PM needs to verify whether the stakeholder engagement plan properly identified the local community and included the required consultation activities.

8
Olusegun A.Olusegun A.Mar 15, 2026

I first leaned toward D because a protest blocking access sounds like a risk that materialized, but the stem is about a consultation that was never done, which is a stakeholder engagement gap. Verify the stakeholder engagement plan first to confirm whether the community was identified and how engagement was scoped. A is the answer.

3
Samuel O.Samuel O.Mar 29, 2026

A is the right call here but I have to say the timing bugs me. In my experience doing plant builds, if you are verifying stakeholder engagement plans days before go-live you already failed months ago. D is tempting because a community shutdown is a realized risk, but the question asks what to verify first and the root cause is a consultation gap, which lives in the stakeholder engagement plan. You check whether that plan actually addressed the natural reserve and local community requirements, then figure out how badly you missed them.

2
Full PMP Practice