PMIPMI
PMP · Question #182
PMP Question #182: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #182. The question stem and answer options stay visible for context.
Submitted by tyler.j· Apr 18, 2026People
Question
The change control board (CCB) has approved a change request to add a new component within a product. The operations manager discovers the change after its approval and complains that the implementation of the change will cause significant disruption to the production line. What should the project manager do first?
Options
- AFormally acknowledge the operation manager's concerns and raise a new risk that the project
- BEscalate the issue to the project sponsor, as the decision to add the component brings many
- CLead a root cause analysis workshop with the design team to identify the failures that led to the
- DMeet with the operations manager to explain the background for the change and understand the
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Change Management#Stakeholder Engagement#Communication#Issue Resolution