A project manager is leading a team of diverse individuals of all ages. The working hours for the project were set at the beginning of the project, and all team members agreed to the hours. However, l

The correct answer is D. Reassess the team's hours collaboratively so that the team is not impeded by the issue. When a team member's personal commitments conflict with agreed-upon working hours, the project manager should collaboratively reassess the team's schedule to find a flexible solution that accommodates the change and maintains team productivity.

Submitted by lucia.co· Apr 18, 2026People

Question

A project manager is leading a team of diverse individuals of all ages. The working hours for the project were set at the beginning of the project, and all team members agreed to the hours. However, later in the project, one of the team members informed the project manager that the previously agreed upon hours no longer work due to the team member's personal commitments. What should the project manager do?

Options

  • ADiscuss the lack of dedication with the team member and their functional manager
  • BAllow the most senior team members to decide the time that works for the team
  • CRemove the team member from the project team to be fair to the other members
  • DReassess the team's hours collaboratively so that the team is not impeded by the issue

How the community answered

(27 responses)
  • A
    4% (1)
  • B
    7% (2)
  • C
    15% (4)
  • D
    74% (20)

Why each option

When a team member's personal commitments conflict with agreed-upon working hours, the project manager should collaboratively reassess the team's schedule to find a flexible solution that accommodates the change and maintains team productivity.

ADiscuss the lack of dedication with the team member and their functional manager

Discussing a 'lack of dedication' is an accusatory and unprofessional response that can damage team morale and trust, failing to address the team member's genuine personal commitments.

BAllow the most senior team members to decide the time that works for the team

Allowing only the most senior team members to decide new hours undermines the initial collaborative agreement and may not address the diverse needs or new commitments of all team members, potentially creating resentment.

CRemove the team member from the project team to be fair to the other members

Removing a team member from the project due to personal commitments is an extreme measure that can lead to loss of expertise, project disruption, and negative team morale, and should only be considered as a last resort after collaborative solutions have failed.

DReassess the team's hours collaboratively so that the team is not impeded by the issueCorrect

When a team member's personal commitments conflict with previously agreed-upon hours, the project manager should collaboratively engage the entire team to reassess working hours. This inclusive approach fosters a supportive environment, promotes team cohesion, and helps find a flexible solution that accommodates the individual's needs while ensuring the project's progress and minimal disruption.

Concept tested: Team Management, Conflict Resolution, Adaptive Leadership

Topics

#Team management#Conflict resolution#Schedule management#Adaptability

Community Discussion

6
Luis F.Luis F.Apr 22, 2026

D is the right call here. PMI loves the collaborative approach, and since the original hours were a team agreement, you work with the team to reassess rather than punishing the person or escalating to their functional manager.

14
Yusuf A.Yusuf A.Apr 22, 2026

Agreed on D, and the senior PM on my team always says the key word in these stems is "reassess" - it tells you the estimate itself is back on the table, not just the person's performance.

0
Yusuf A.Yusuf A.Apr 9, 2026

D is the answer here. My senior PM always says collaborative problem solving beats punitive action, but I am curious, would the answer change if the team had already signed off on a team charter with those specific hours documented?

1
Luis F.Luis F.Apr 11, 2026

Good point Yusuf but a charter with documented hours actually reinforces D because the collaborative approach would reference that agreement as the baseline for the conversation rather than jumping to enforcement.

0
Ingrid P.Ingrid P.Apr 15, 2026

C is the call here. The team charter and ground rules were set and agreed by everyone, so when a member cannot honor that commitment the PM has to enforce accountability and remove them rather than renegotiate terms mid-project and signal that the agreement is optional.

0
Yusuf A.Yusuf A.Apr 17, 2026

D is the right call here Ingrid. A senior PM at my company showed me that when someone cant honor a commitment the first move is to talk with them and renegotiate or adjust the agreement, not jump straight to removal, especially if the charter was meant to be a living document.

0
Full PMP Practice