nerdexam
PMI

PMP · Question #1417

A team is working on a hybrid project. Due to different interpretations of the project requirements, the deliverables are not aligned to the expectations. What steps should the project manager have…

The correct answer is A. Ensure the team understands all additional project requirements. To prevent misalignment due to differing interpretations of requirements, the project manager should have proactively ensured that the entire team clearly understood all project requirements and expectations from the outset.

Submitted by carlos_mx· Apr 18, 2026People

Question

A team is working on a hybrid project. Due to different interpretations of the project requirements, the deliverables are not aligned to the expectations. What steps should the project manager have taken to prevent this?

Options

  • AEnsure the team understands all additional project requirements.
  • BEnsure the team receives continuous feedback from customers/users.
  • CUpdate the project management plan in order to get back on track.
  • DSubmit a change request to adjust the project scope.

How the community answered

(45 responses)
  • A
    87% (39)
  • B
    4% (2)
  • C
    2% (1)
  • D
    7% (3)

Why each option

To prevent misalignment due to differing interpretations of requirements, the project manager should have proactively ensured that the entire team clearly understood all project requirements and expectations from the outset.

AEnsure the team understands all additional project requirements.Correct

The root cause of deliverables not aligning with expectations due to different interpretations of requirements is a lack of shared understanding. The project manager's preventative action should be to ensure thorough communication and confirmation that all team members fully comprehend all project requirements, eliminating ambiguity from the start.

BEnsure the team receives continuous feedback from customers/users.

Continuous feedback from customers/users is crucial for validation and adaptation in agile and hybrid projects, but it addresses discovering new needs or validating existing interpretations, not preventing initial misinterpretations among the team.

CUpdate the project management plan in order to get back on track.

Updating the project management plan is a reactive measure taken after the problem has occurred, not a preventative step to avoid the initial misinterpretation.

DSubmit a change request to adjust the project scope.

Submitting a change request to adjust scope is a reactive measure to address a misalignment that has already occurred, not a preventative action to ensure initial understanding of requirements.

Concept tested: Requirements elicitation and communication

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok/collect-requirements

Topics

#Requirements Management#Communication Management#Shared Understanding#Hybrid Projects

Community Discussion

No community discussion yet for this question.

Full PMP Practice