PMP · Question #1344
PMP Question #1344: Real Exam Question with Answer & Explanation
The correct answer is A: Consider the view of each team member about the issue in order to reach consensus.. When team members intensely disagree on a technical approach, the project manager should facilitate a discussion to understand each viewpoint and guide the team towards a consensus decision.
Question
In the planning phase of a software implementation project, two of the team members disagree on how to approach end-user training. The discussion has intensified and the team members are not able to agree. What should the project manager do next?
Options
- AConsider the view of each team member about the issue in order to reach consensus.
- BMake a decision based on expert judgment as a project manager.
- CRemove both team members since they are not productively adding to the team.
- DRemove one or the team members from the project to improve team dynamics.
Explanation
When team members intensely disagree on a technical approach, the project manager should facilitate a discussion to understand each viewpoint and guide the team towards a consensus decision.
Common mistakes.
- B. While a project manager can use expert judgment, in situations of team disagreement, it's generally better to facilitate team consensus where possible, as it leads to greater buy-in and ownership of the solution.
- C. Removing team members is an extreme measure and punitive, which would severely damage team morale and project productivity, and should only be considered as a last resort for severe performance or behavioral issues.
- D. Removing one team member without attempting to resolve the conflict is premature and similarly detrimental to team dynamics and trust.
Concept tested. Conflict resolution and consensus building
Topics
Community Discussion
No community discussion yet for this question.