A project manager uses a laissez-faire leadership style with a newly hired project team. The project manager quickly notices that team members are underperforming, the schedule is delayed, and the pro

The correct answer is C. Established goals and provided the project team with sufficient authority to work. A project manager should have established clear goals and delegated appropriate authority at the project's start, even with a new team, to foster clear direction and effective execution.

Submitted by femi9· Apr 18, 2026People

Question

A project manager uses a laissez-faire leadership style with a newly hired project team. The project manager quickly notices that team members are underperforming, the schedule is delayed, and the project is overbudget. What should the project manager have done at the start of the project?

Options

  • AManaged the team as necessary and allowed them to work on their own
  • BAdapted a direct management style according to the project team's needs
  • CEstablished goals and provided the project team with sufficient authority to work
  • DAdapted a servant leader management style to support the team's development

How the community answered

(62 responses)
  • A
    13% (8)
  • B
    5% (3)
  • C
    74% (46)
  • D
    8% (5)

Why each option

A project manager should have established clear goals and delegated appropriate authority at the project's start, even with a new team, to foster clear direction and effective execution.

AManaged the team as necessary and allowed them to work on their own

Simply allowing the team to work on their own, especially when new, is exactly the laissez-faire approach that led to problems; effective management involves more structure initially.

BAdapted a direct management style according to the project team's needs

While adapting a direct management style *might* be necessary given the issues, the fundamental preventative step at the start is to establish goals and authority, which can be done without necessarily being overly direct from day one, but certainly not laissez-faire.

CEstablished goals and provided the project team with sufficient authority to workCorrect

A laissez-faire approach is generally not suitable for a newly hired team that may lack established norms, processes, or clear understanding of expectations. At the start of a project, it's essential for the project manager to establish clear goals, define roles, and provide sufficient guidance and authority to empower the team while ensuring they understand their responsibilities and expected outcomes.

DAdapted a servant leader management style to support the team's development

A servant leader style is beneficial for supporting and enabling the team, but even a servant leader needs to ensure clear goals and empowerment are in place, which aligns more closely with choice C than D as the *initial* critical step for a new team.

Concept tested: Project leadership styles and team development

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok/leadership-styles

Topics

#Leadership styles#Team management#Goal setting#Delegation