nerdexam
PMIPMI

PMP · Question #1296

PMP Question #1296: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1296. The question stem and answer options stay visible for context.

Submitted by anjalisingh· Apr 18, 2026People

Question

A project sponsor is concerned that the scope is not being met correctly and has questioned several team members about this individually. When the project sponsor approached the project manager, the project manager realized that the issue was that the project sponsor understood the scope in a different manner than the project team. What should the project manager do to address this issue?

Options

  • AFacilitate a stakeholder alignment session so that the team and project sponsor are in agreement
  • BSet up a daily standup and request that the project sponsor attend to understand the project's
  • CAsk the project team to compile a project scope document and obtain approval from the project
  • DRequest that the project team change their task deliverables to reflect the project sponsor's

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Stakeholder Management#Scope Management#Communication#Issue Resolution
Full PMP PracticeBrowse All PMP Questions