nerdexam
PMIPMI

PMP · Question #1273

PMP Question #1273: Real Exam Question with Answer & Explanation

The correct answer is A: Communicate the project's impact and plans to engage the project team throughout the project.. To address team pessimism in a project that might seem negative, the project manager must communicate effectively about the project's purpose and how the team will be involved.

Submitted by ravi_2018· Apr 18, 2026People

Question

A company has decided to initiate a project to eliminate a sales channel that has been unprofitable for the past 3 years. Some members of the project team are pessimistic about the project. What should the project manager do in this situation?

Options

  • ACommunicate the project's impact and plans to engage the project team throughout the project.
  • BEngage the functional managers to describe the project's impact to the team members directly.
  • CEscalate the team's concerns and ask the project sponsor to change the team's composition.
  • DProvide team members with specific and clear instructions on the project objectives and tasks.

Explanation

To address team pessimism in a project that might seem negative, the project manager must communicate effectively about the project's purpose and how the team will be involved.

Common mistakes.

  • B. Engaging functional managers to communicate on the project manager's behalf is delegating a core responsibility and could dilute the message or be less effective than direct communication from the project manager.
  • C. Escalating team concerns to the sponsor and requesting a team change without first attempting to address the root cause of pessimism is an overreaction and could demotivate the existing team further.
  • D. While clear instructions are important, simply providing objectives and tasks without addressing the underlying pessimism about the project's purpose will not resolve the motivational issue; it treats a symptom, not the cause.

Concept tested. Project team motivation and communication

Topics

#Team Motivation#Communication Management#Stakeholder Engagement#Project Leadership

Community Discussion

No community discussion yet for this question.

Full PMP PracticeBrowse All PMP Questions