nerdexam
PMIPMI

PMP · Question #1216

PMP Question #1216: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1216. The question stem and answer options stay visible for context.

Submitted by yaw92· Apr 18, 2026People

Question

A globally distributed project team is running behind schedule due to the lack of team commitment and low morale. In order to bring the schedule back on track, what should the project manager do first?

Options

  • ASet up a meeting to perform a root cause analysis.
  • BPermanently colocate the team for better performance.
  • CUpdate the issue log and communicate it to the team.
  • DSeek the sponsor's approval to extend the project schedule.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Team Performance#Problem Solving#Root Cause Analysis#Schedule Recovery
Full PMP PracticeBrowse All PMP Questions