PMIPMI
PMP · Question #120
PMP Question #120: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #120. The question stem and answer options stay visible for context.
Submitted by brentm· Apr 18, 2026People
Question
A project is behind schedule because of a delayed equipment installation. This is affecting many other activities. The manager responsible for the equipment delivery notified the project manager that there is a capacity issue for the team doing the installation. What should the project manager have done to prevent this situation from happening?
Options
- ADefined the skill requirements more clearly in the scope statement.
- BAsked the manager to follow the agreed-upon resource management plan.
- CConducted periodic reviews with the manager on resource availability.
- DConsulted with the installation team on a regular basis to check for conflicts.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Resource Management#Resource Availability#Proactive Monitoring#Stakeholder Communication