PMP · Question #1192
A project team is identifying project risks for a bridge to be built across a river. The team needs to send out invitations for a risk workshop to better understand the risks involved. Which distribut
The correct answer is A. Team members, consultants from outside the project with experience in the field, and the. Based on the information provided by PMI-PMP, the project manager should use distribution list A when sending out invitations for the risk workshop. This distribution list includes team members, consultants from outside the project with experience in the field, and the customer.
Question
Options
- ATeam members, consultants from outside the project with experience in the field, and the
- BFunctional managers, team members, and external consultants with experience in the field
- CWeather experts, functional managers, and team members
- DTeam members, engineers, and weather experts
How the community answered
(47 responses)- A74% (35)
- B13% (6)
- C4% (2)
- D9% (4)
Explanation
Based on the information provided by PMI-PMP, the project manager should use distribution list A when sending out invitations for the risk workshop. This distribution list includes team members, consultants from outside the project with experience in the field, and the customer. Including these stakeholders in the risk workshop will help ensure that all potential risks are identified and addressed in a timely manner.
Topics
Community Discussion
No community discussion yet for this question.