A project team is identifying project risks for a bridge to be built across a river. The team needs to send out invitations for a risk workshop to better understand the risks involved. Which distribut

The correct answer is A. Team members, consultants from outside the project with experience in the field, and the. Based on the information provided by PMI-PMP, the project manager should use distribution list A when sending out invitations for the risk workshop. This distribution list includes team members, consultants from outside the project with experience in the field, and the customer.

Submitted by andreas_gr· Apr 18, 2026People

Question

A project team is identifying project risks for a bridge to be built across a river. The team needs to send out invitations for a risk workshop to better understand the risks involved. Which distribution list should the project manager use when sending out invitations?

Options

  • ATeam members, consultants from outside the project with experience in the field, and the
  • BFunctional managers, team members, and external consultants with experience in the field
  • CWeather experts, functional managers, and team members
  • DTeam members, engineers, and weather experts

How the community answered

(47 responses)
  • A
    74% (35)
  • B
    13% (6)
  • C
    4% (2)
  • D
    9% (4)

Explanation

Based on the information provided by PMI-PMP, the project manager should use distribution list A when sending out invitations for the risk workshop. This distribution list includes team members, consultants from outside the project with experience in the field, and the customer. Including these stakeholders in the risk workshop will help ensure that all potential risks are identified and addressed in a timely manner.

Topics

#Risk Identification#Stakeholder Engagement#Workshops