PMP · Question #115

PMP Question #115: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #115. The question stem and answer options stay visible for context.

Submitted by jakub_pl· Apr 18, 2026People

Question

A company has a transformation project in progress. During a planning session, several stakeholders are in constant disagreement and often use personal arguments to support their position. Team members are getting frustrated with the situation. What should the project manager have done to avoid this situation?

Options

  • AEstablished ground rules before the discussion had started
  • BReinforced that higher-level management has the decision power
  • CInvited a high-level sponsor to the meeting to reduce the level of disagreement
  • DAsked stakeholders not to voice their opinions during the meeting

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Conflict Management#Meeting Facilitation#Ground Rules#Stakeholder Engagement