PMIPMI
PMP · Question #1118
PMP Question #1118: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #1118. The question stem and answer options stay visible for context.
Submitted by minji_kr· Apr 18, 2026People
Question
A project manager held a meeting and framed the project schedule. A critical stakeholder, who was not consulted at the time of the schedule discussion, complained that the published dates are not agreeable due to a prescheduled task for another assignment. What should the project manager do first?
Options
- AOrganize a new schedule framing meeting with the critical stakeholder to obtain input.
- BDiscuss with the project sponsor and create a new project schedule.
- CAnalyze the root cause of the issue and update the communications management plan.
- DReach out to the project sponsor and request additional resources.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Stakeholder Engagement#Communication Management#Schedule Management#Issue Resolution