Question
A project manager discovered that a component on the critical path is in danger of delay due to continuous disagreements between two developers. This personality-related issue can't be resolved by the team. What should the project manager do?
Options
- ALog the issue in the register and delay the development of the component.
- BLog the issue in the register and ask the team to make a decision by voting.
- CLog the issue in the register and escalate to the human resources (HR) manager.
- DLog the issue in the register and let the developers resolve the conflict.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Conflict Resolution#Team Leadership#Escalation Management#Interpersonal Skills