nerdexam
PMIPMI

PMP · Question #1081

PMP Question #1081: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1081. The question stem and answer options stay visible for context.

Submitted by skyler.x· Apr 18, 2026People

Question

A client has requested that a product be implemented in 4 months and is ready to increase their budget to do this quickly. The project manager cannot comply with the request with the current resources or even additional resources. The project manager estimates that 8 to 12 months are needed for the product to go live. What should the project manager do to address this situation?

Options

  • AMotivate the team to work more efficiently and approve overtime in order to meet the client's goal
  • BSeek additional resources from the subcontractors and other sources to parallelize the necessary
  • CDiscuss with the client alternative approaches to deliver the minimal viable product (MVP) in 4
  • DCall a meeting with the client so they will understand that 4 months is not enough time to deliver

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Stakeholder Engagement#Scope Management#Negotiation#Agile Principles
Full PMP PracticeBrowse All PMP Questions