nerdexam
PMIPMI

PMP · Question #1078

PMP Question #1078: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1078. The question stem and answer options stay visible for context.

Submitted by kavita_s· Apr 18, 2026People

Question

A project team has identified a risk and wants to accept it as an opportunity to finish a project earlier than planned. The project manager realizes that the sponsor may not accept the risk since the sponsor is risk averse. What should the project manager do?

Options

  • ACreate a contingency reserve to cover the risk in order to ensure that the risk will be accepted.
  • BConduct a Monte Carlo analysis to determine if the team will complete the project early.
  • CExplain to the sponsor that this is a nonevent type of risk and it will be fine to accept it.
  • DConvince the sponsor that this will cost less, ultimately resulting in more profit for the sponsor.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk Opportunity#Stakeholder Engagement#Communication Strategy#Business Value
Full PMP PracticeBrowse All PMP Questions