PMP · Question #1002
PMP Question #1002: Real Exam Question with Answer & Explanation
The correct answer is D: Contact the functional manager and develop a mitigation strategy.. Upon learning of a team member's impending resignation, the project manager should immediately collaborate with the functional manager to develop a strategy that mitigates the risk to project delivery.
Question
Before a daily standup, a team member informed the project manager that they have accepted a job offer at another company. The team member explains that they plan to present their resignation to the functional manager. What should the project manager do next?
Options
- AContact the product owner and review the current sprint backlog.
- BCommunicate to the team members at the daily standup.
- CAlert the functional manager about possible delivery delays.
- DContact the functional manager and develop a mitigation strategy.
Explanation
Upon learning of a team member's impending resignation, the project manager should immediately collaborate with the functional manager to develop a strategy that mitigates the risk to project delivery.
Common mistakes.
- A. Reviewing the sprint backlog with the product owner is a subsequent step after addressing the immediate resource change with the functional manager.
- B. Communicating a team member's resignation to the entire team at the daily standup without a clear plan or understanding of the situation from the functional manager could create unnecessary anxiety or uncertainty.
- C. Alerting the functional manager about possible delays without simultaneously working on a mitigation strategy is incomplete and less proactive than developing a strategy together.
Concept tested. Resource management, risk mitigation, stakeholder communication
Reference. https://www.pmi.org/pmbok-guide-standards/foundational/pmbok
Topics
Community Discussion
No community discussion yet for this question.