PMI-ACP · Question #548
PMI-ACP Question #548: Real Exam Question with Answer & Explanation
The correct answer is D: Team Attendance. Agile KPIs track delivery performance, quality, and team capability. Actual stories completed vs. committed (A) measures predictability, quality delivered (B) tracks customer satisfaction, team enthusiasm (C) is sometimes tracked as a morale/health metric, team velocity (E) measu
Question
Which of the following is NOT a KPI (key performance indicator) of Agile?
Options
- AActual Stories Completed vs. Committed Stories
- BQuality Delivered to Customers
- CTeam Enthusiasm
- DTeam Attendance
- ETeam Velocity
- FTechnical Debt Management
Explanation
Agile KPIs track delivery performance, quality, and team capability. Actual stories completed vs. committed (A) measures predictability, quality delivered (B) tracks customer satisfaction, team enthusiasm (C) is sometimes tracked as a morale/health metric, team velocity (E) measures throughput, and technical debt management (F) tracks code health. Team Attendance (D) is an HR/operational metric with no direct tie to Agile performance — it does not reflect how effectively the team delivers working software.
Topics
Community Discussion
No community discussion yet for this question.