PMI-ACP · Question #492
PMI-ACP Question #492: Real Exam Question with Answer & Explanation
The correct answer is D: The Development Team. According to the Scrum Guide, the Development Team is responsible for tracking their own work and updating the Sprint Backlog, including remaining work, throughout the Sprint. This reflects the self-organizing nature of the Development Team. The Scrum Master is a servant-leader a
Question
Who updates work remaining during the Sprint?
Options
- BThe Product Owner
- CThe Scrum Master
- DThe Development Team
Explanation
According to the Scrum Guide, the Development Team is responsible for tracking their own work and updating the Sprint Backlog, including remaining work, throughout the Sprint. This reflects the self-organizing nature of the Development Team. The Scrum Master is a servant-leader and facilitator, not a tracker of work. The Product Owner manages the Product Backlog, not the Sprint Backlog internals.
Topics
Community Discussion
No community discussion yet for this question.