PMI-ACP · Question #492

PMI-ACP Question #492: Real Exam Question with Answer & Explanation

The correct answer is D: The Development Team. According to the Scrum Guide, the Development Team is responsible for tracking their own work and updating the Sprint Backlog, including remaining work, throughout the Sprint. This reflects the self-organizing nature of the Development Team. The Scrum Master is a servant-leader a

Submitted by khalil_dz· Apr 18, 2026Team Performance

Question

Who updates work remaining during the Sprint?

Options

  • BThe Product Owner
  • CThe Scrum Master
  • DThe Development Team

Explanation

According to the Scrum Guide, the Development Team is responsible for tracking their own work and updating the Sprint Backlog, including remaining work, throughout the Sprint. This reflects the self-organizing nature of the Development Team. The Scrum Master is a servant-leader and facilitator, not a tracker of work. The Product Owner manages the Product Backlog, not the Sprint Backlog internals.

Topics

#Scrum Roles#Development Team Responsibilities#Sprint Backlog#Work Remaining