PMI-ACP · Question #288

PMI-ACP Question #288: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-ACP to reveal the answer and full explanation for question #288. The question stem and answer options stay visible for context.

Submitted by viktor_hu· Apr 18, 2026Team Performance

Question

Typically calculated in story points, this is the rate at which the team converts "Done" items in a single Sprint:

Options

  • ABurndown rate
  • BBurn-up rate
  • CVelocity
  • DCapacity

Unlock PMI-ACP to see the answer

You've previewed enough free PMI-ACP questions. Unlock PMI-ACP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Velocity#Story points#Agile metrics#Sprint management